The coming construction of the new Center for Science and Innovation (CSI)—which necessitates the demo of the University Services Building (USVC)—and the recent opening of a new location for the Campus Store and Vi Hilbert Hall, have resulted in a sequence of office moves.
Below are the new locations for offices and services that have been or soon will be relocated from USVC; in some instances, there will be a brief discontinuation of the services as the moves occur:
Office/Service | New Location | Date of Move |
---|---|---|
Campus Store | Madison Building (MADI) at 12th and Madison | January 2018 |
Enrollment Services | Vi Hilbert Hall (HILB) | November 2018 |
University Budget Office | Engineering, 6th Floor (ENGR) | March 25, 2019 |
University Core | Administration Building, south wing, 1st floor (ADMN) | March 2019 |
Office of Sponsored Projects | Hunthausen 120 (HUNT) | March 2019 |
Department of Public Safety | 1313 Columbia, room 002 (CLMB) | April 1, 2019 |
Demarc (telecommunications system) | Campus Data Center, ENGR 6th floor | Mid- to late April 2019 |
Lactation Room | ADMN 200 | May 2019 |
US Bank ATM | Pigott, PACCAR Atrium (PIGT) | April 2019 |
USPS Mailbox | TBD by USPS | April 2019 |
In addition, the following offices have relocated as a result of new spaces made available in relation to Vi Hilbert Hall’s opening.
Office | New Location | Date of Move |
---|---|---|
University Advancement |
Advancement and Alumni Building (ADAL) at 12th and Marion (in space freed by Admissions move to Vi Hilbert Hall) |
February 2019 |
Academic Affairs programs and staff |
ADMN, south wing, 1st floor (Global Engagement and other faculty/staff join Core in Advancement's former location) |
March-April 2019 |
Office of Diversity and Inclusion | ADMN, south wing, 1st floor | May 2019 |
For updates on the construction of the Center for Science and Innovation and related enabling projects, visit the Design and Construction website.